Construction Progress
David's Residence — shareable link for investors and buyers
Overall Progress
Live30%complete
Milestones
- ✓
Site Clearing & Setting Out
Target: 5% — completed 15 September 2026
- ✓
Foundation
Target: 20% — completed 15 September 2026
- ✓
Structural Frame (1st Floor Slab)
Target: 30% — completed 22 September 2026
Roofing
Target: 60%
Blockwork & Plastering
Target: 75%
Finishing (Fittings, Electrical, Plumbing)
Target: 90%
Handover
Target: 100%
Progress Updates
22 September 2026
Structural Frame (1st Floor Slab)
30% at this update
15 September 2026
The foundation level has been completed; we have begun the substructure phase.
20% at this update